Installation Guide for asphalt mixing plant
Mixing equipment installation
1, site
(1) principles of large asphalt mixing plant covers an area of large, stone stack must have a certain amount of storage capacity. When choosing venues, this section should be near the embankment, and located near the midpoint of the bid, sources of water, electricity, raw material and finished product in and out of traffic.
(2) natural ground environment site should be dry, the terrain is slightly higher, and lower the water table, choose a good geological conditions of the site, you can reduce the cost of installation, avoid the equipment variants of the settlement. Due to the moisture content of raw material for the production of asphalt mixing plant has a large impact, high moisture, increased fuel consumption, production capacity will decline, increasing utility costs and, therefore, must have good drainage system around the equipment.
2, installation
(1) preparations for installation
1. all ancillary equipment and all equipment prior to arrival at the site, drawing assemblies with each other based on the location map, for when installing a lift to be successful;
2. the installation site should meet the requirements, and achieve "three connections and one leveling";
3. Organization a experienced installation team access to the construction site and installation staff is as follows:
Organizer 1, 2 technicians (mechanical engineer, electrical engineer, 1), installation fitter 4, installing electrician 2, electric welder 1, management workers 1, rigger 1, labour 4-6, civil engineering 2.
(2) installing the required equipment
Steam crane (lifting capacity according to the largest parts selection); Jack 5T 1, 30m line 1, 10m 1 telescopic ladders, ladder 1 3M above, crowbar, hammer, large shears, hand saw, grinder, pliers, level gauge, wrench, belt and other commonly used tools are available, the ZL50 loader 1.