Installation points of asphalt mixing plant

2017-09-05 16:31:52

The installation of asphalt mixing plant has 2 aspects, basic setting and equipment installation.
1. The basic settings. Prepare the site according to the plane plan of the equipment to ensure that all vehicles are available to move. The foot bolts of the body should be properly moved in the foundation hole in order to adjust the position of the leg. Use the appropriate lifting device to put the legs in place and install the connecting rod to the top of the leg. Pour the mortar into the foundation hole, until the cement is hard, put the washers and nuts placed on the anchor bolts, and then fasten the legs in place.

asphalt mixing plant

2. The equipment installation.
①Install the bottom platform to operate the crane to lift the bottom floor of the floor so that it falls on the legs and insert the locating pins on the legs into the corresponding holes in the platform floor and with bolts.
②Install the hot hopper to lift the hoisting machine up to the vertical position, then place it on the bottom and install the support bar and bolt to prevent it from swinging and turning. And then align the discharge chute to the connection port on the shaker cover.
③Install the drying drum Place the drying drum in place, install the legs and support bars. Open the dust seal on the hopper and connect the discharge chute of the drying drum to the feed tank of the hot hopper. Adjust the inclination angle of the drying drum in place by adjusting the height of the retractable leg at the feed end of the drying drum. Fit the burner to the mounting flange and tighten the mounting bolts and adjust them to the exact position.
④Install the Tilting Tape Conveyor and Vibrating Screen The tilted belt conveyor is lifted in place so that it is connected to the feed tank of the drying drum. When installing the vibrating screen, it should be in its position to prevent the material from deviating and to ensure that the vibrating screen is tilted at the desired angle in the length direction.
⑤Installation of the asphalt system components will have a separate chassis asphalt pump in place, so that it is installed with the asphalt insulation tank and mixing device body connected to the asphalt pump into the pipeline at the lowest point to install a discharge valve. Asphalt conveying lines should be inclined, the inclination angle should be not less than 5 °, so that asphalt can flow smoothly. When installing asphalt piping, the height should ensure that the following vehicles pass smoothly.
⑥Asphalt three-way valve is located above the asphalt weighing bucket, the installation should be removed before the valve plug, a rod-like lubrication seal into the valve body, put back and tighten the cocks. The wiring and installation of electrical equipment must be carried out by qualified electricians.


Pre:Top advantages of haomei asphalt mixing plant for sale

Next:Requirements of operate asphalt drum mix plant

■ Inquiry
Your name :
Your tel :
* Your mail :
Your country :
Your address :
* Inquiry :